  • Noksan

Noksan national industrial complex

current condition

Noksan national industrial complex
  • location : the area of Songjeongdong Gangseogu Busan
  • size : 6,972,000㎡
  • project cost : 1 trillion 16.7 billion won
  • project period : 1990~2003
  • business type : assembled metal, precision machine, petrochemical, cotton clothing etc.

work in progress

work in progress
1992. Mar. 19 development plan notice (Ministry of Construction & Transportation No.25)
1999. Aug. 31 1st step construction project initiation permit
1999. Jul. 8 Noksan district 1st & 2nd step performance plan change permit
2001. Apr. 12 Noksan district 3rd & 4th step performance plan change permit
2003. Feb. 28 project completion